VB26/06-IG06 @audrey_yap

STATUS: IN PRODUCTION
PRODUCTION PROGRESS
( 650 / 1300 ) ITEMS
30%

20-06-2026

- ( 500 ) Mock Tickets and ( 500 ) random Magnetic Bookmarks order placed. 1st Payment received, shipping to be calculated after items completed production.

10-08-2026

- Add-on ( 150 ) Mock Tickets and ( 150 ) random Magnetic Bookmark. Payment received.


05-09-2026

- Production starts on 07.09.2026

07-09-2026

- Production has started. Magnetic bookmark production will begin once the mock tickets are completed.

- Printing in progress for ( 650 ) pcs mock ticket.

08-09-2026

- Printing in progress for ( 650 ) pcs mock ticket.

09-09-2026

- Printing in progress for ( 650 ) pcs mock ticket.

10-09-2026

- Printing in progress for ( 650 ) pcs mock ticket.

11-09-2026

- Printing in progress for ( 650 ) pcs mock ticket.

12-09-2026

- No Production today. Production resumes on 14.09.2026.

- Magnetic bookmark design and quantity finalized.


14-09-2026

- Printing in progress for ( 650 ) pcs mock ticket.

15-09-2026

- Printing in progress for ( 650 ) pcs mock ticket.

16-09-2026

- Printing completed for ( 650 ) pcs mock ticket.

17-09-2026

- Laminating in progress for ( 650 ) pcs mock ticket.

18-09-2026

- Laminating completed. Cutting in progress for ( 650 ) pcs mock tickets.

19-09-2026

- No Production today. Production resumes on 23.09.2026.

23-09-2026

- Cutting in progress for ( 650 ) pcs mock tickets.
- ( 650 ) pcs mock tickets completed.

24-09-2026

- Production started for ( 650 ) pcs magnetic bookmark.

25-09-2026

- No Production today. Production resumes on 28.09.2026.

28-09-2026

- Production in progress ( 650 ) pcs magnetic bookmark.